Skip Navigation
Welcome

On Our Site
Welcome to the official website for Lynnfield, Massachusetts!
This table is used for column layout.
Town Seal of Lynnfield
 
Road Resurfacing
 2011 ROAD CONSTRUCTION PROGRAM
& SCHEDULE OF WORK
(last updated: September 26, 2011)
The Public Works Department has listed the following streets to be resurfaced during the 2011 construction season:

SALEM STREET ( Maple Street to Route 1)


June 21st-July 8th
Install granite curbing(expect delays)
Completed
July 19th-20th
Mill existing roadway (expect delays)
Completed
July 25th-26th
Raise castings to grade (expect delays)
Completed
August 1st
Install new finish asphalt (expect delays)
Completed
Aug. 2st-31st
Repair sidewalk and driveway aprons (expect delays)
Completed
Aug. 12th-31st
Loam and seed
Completed

During construction there will be DELAYS and possible DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.


BROOK DRIVE(Entire Length)


June 20th
Remove asphalt curbing
Completed
June 27th-July 5th
Install granite curbing(expect delays)
Completed
July 19th-20th
Mill existing roadway(expect delays)
Completed
July 25th-26th
Raise castings to grade(expect delays)
Completed
August 1st
Install new finish apshalt(expect delays)
Completed
Sept. 12nd-Sept.30th
Repair Sidewalk and driveway aprons, as necessary
On Schedule
Aug. 11th-15th
Loam and seed
Completed

During construction there will be DELAYS and possible DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.

MAIN STREET (IN THE VICINITY OF #1414)


July 19th-July 20st
Mill existing roadway(expect delays)
Completed
July 25th-26th
Raise castings to grade(expect delays)
Completed
August 17th
Install new finish asphalt(expect delays)
Completed
Oct. 3rd-14th
Repair driveway aprons(if necessary)
On Schedule
Oct. 3rd-14th
Loam and seed
On Schedule

MAIN STREET (MIDDLETON LINE TO FRIENDSHIP LANE)


July 19th-20th
Mill existing roadway(expect delays)
Completed
July 25th-26th
Raise castings to grade(expect delays)
Completed
August 17th
Install new finish asphalt(expect delays)
Completed
Oct. 3rd-14th
Repair driveway aprons(if necessary)
On Schedule
Oct. 3rd-14th
Loam and seed
On Schedule

MAIN STREET (#368-#395)


July 19th-20th
Mill existing roadway(expect delays)
Completed
July 25th-26th
Raise castings to grade(expect delays)
Completed
August 17th
Install new finish asphalt(expect delays)
Completed
Oct. 3rd-14th
Repair driveway aprons(if necessary)
On Schedule
Oct. 3rd-14th
Loam and seed
On Schedule

MAIN STREET (VICINITY OF OLD TOWNE ROAD)


July 19th-20th
Mill existing roadway(expect delays)
Completed
July 25th-26th
Raise castings to grade(expect delays)
Completed
August 17th
Install new finish asphalt(expect delays)
Completed
Oct. 3rd-14th
Repair driveway aprons(if necessary)
On Schedule
Oct. 3rd-14th
Loam and seed
On Schedule

During construction there will be DELAYS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.

MAGNOLIA TERRACE


July 25th-26th
Remove asphalt curb
Completed
July 25th-26th
Lower castings
Completed
August 2nd & 3rd
Reclaim and grade roadway(expect delays)
Completed
August 8th
Install binder asphalt(expect delays)
Completed
August 10th
Raise castings
Completed
August 12th
Install granite curbing at road roundings and handi-cap ramps
Completed
August 18th
Install finish course of asphalt(expect delays)
Completed
August 23rd
Install asphalt curbing
Completed
September 26th-30th
Repair driveway aprons(as needed)
On Schedule
Oct. 1st-Oct.4th
Loam and seed
On Schedule






 
Website Disclaimer
Town of Lynnfield, 55 Summer St., Lynnfield, MA 01940
Privacy Statement
Virtual Towns & Schools Website