2011 ROAD CONSTRUCTION PROGRAM
& SCHEDULE OF WORK
(last updated: September 26, 2011)
The Public Works Department has listed the following streets to be resurfaced during the 2011 construction season:
SALEM STREET ( Maple Street to Route 1)
June 21st-July 8th |
Install granite curbing(expect delays) |
Completed |
July 19th-20th |
Mill existing roadway (expect delays) |
Completed |
July 25th-26th |
Raise castings to grade (expect delays) |
Completed |
August 1st |
Install new finish asphalt (expect delays) |
Completed |
Aug. 2st-31st |
Repair sidewalk and driveway aprons (expect delays) |
Completed |
Aug. 12th-31st |
Loam and seed |
Completed |
During construction there will be DELAYS and possible DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
BROOK DRIVE(Entire Length)
June 20th |
Remove asphalt curbing |
Completed |
June 27th-July 5th |
Install granite curbing(expect delays) |
Completed |
July 19th-20th |
Mill existing roadway(expect delays) |
Completed |
July 25th-26th |
Raise castings to grade(expect delays) |
Completed |
August 1st |
Install new finish apshalt(expect delays) |
Completed |
Sept. 12nd-Sept.30th |
Repair Sidewalk and driveway aprons, as necessary |
On Schedule |
Aug. 11th-15th |
Loam and seed |
Completed |
During construction there will be DELAYS and possible DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
MAIN STREET (IN THE VICINITY OF #1414)
July 19th-July 20st |
Mill existing roadway(expect delays) |
Completed |
July 25th-26th |
Raise castings to grade(expect delays) |
Completed |
August 17th |
Install new finish asphalt(expect delays) |
Completed |
Oct. 3rd-14th |
Repair driveway aprons(if necessary) |
On Schedule |
Oct. 3rd-14th |
Loam and seed |
On Schedule |
MAIN STREET (MIDDLETON LINE TO FRIENDSHIP LANE)
July 19th-20th |
Mill existing roadway(expect delays) |
Completed |
July 25th-26th |
Raise castings to grade(expect delays) |
Completed |
August 17th |
Install new finish asphalt(expect delays) |
Completed |
Oct. 3rd-14th |
Repair driveway aprons(if necessary) |
On Schedule |
Oct. 3rd-14th |
Loam and seed |
On Schedule |
MAIN STREET (#368-#395)
July 19th-20th |
Mill existing roadway(expect delays) |
Completed |
July 25th-26th |
Raise castings to grade(expect delays) |
Completed |
August 17th |
Install new finish asphalt(expect delays) |
Completed |
Oct. 3rd-14th |
Repair driveway aprons(if necessary) |
On Schedule |
Oct. 3rd-14th |
Loam and seed |
On Schedule |
MAIN STREET (VICINITY OF OLD TOWNE ROAD)
July 19th-20th |
Mill existing roadway(expect delays) |
Completed |
July 25th-26th |
Raise castings to grade(expect delays) |
Completed |
August 17th |
Install new finish asphalt(expect delays) |
Completed |
Oct. 3rd-14th |
Repair driveway aprons(if necessary) |
On Schedule |
Oct. 3rd-14th |
Loam and seed |
On Schedule |
During construction there will be DELAYS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
MAGNOLIA TERRACE
July 25th-26th |
Remove asphalt curb |
Completed |
July 25th-26th |
Lower castings |
Completed |
August 2nd & 3rd |
Reclaim and grade roadway(expect delays) |
Completed |
August 8th |
Install binder asphalt(expect delays) |
Completed |
August 10th |
Raise castings |
Completed |
August 12th |
Install granite curbing at road roundings and handi-cap ramps |
Completed |
August 18th |
Install finish course of asphalt(expect delays) |
Completed |
August 23rd |
Install asphalt curbing |
Completed |
September 26th-30th |
Repair driveway aprons(as needed) |
On Schedule |
Oct. 1st-Oct.4th |
Loam and seed |
On Schedule |
|