Road Resurfacing
 2010 ROAD CONSTRUCTION PROGRAM
& SCHEDULE OF WORK
(last updated: September 8, 2010)
The Public Works Department has listed the following streets to be resurfaced during the 2010 construction season:

SALEM STREET ( Summer Street to Maple Street)


June 21st-22nd
Mill off top surface of pavement(expect delays)
Completed
July 28th-29th
Raise casting to grade (expect delays)
Completed
June 28th- Aug. 18th
Install new granite curbing (expect delays)
Completed
August 31st
Install finish pavement (expect delays)
Completed
Sept 14th
Stripe roadway
On schedule
Sept.1st-14th
Loam and seed
On schedule
July 26th-Sept 7th
Repair sidewalk and driveway aprons as necessary
Completed

During construction there will be DELAYS and DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.


THOMAS ROAD(Entire Length)


June 14th-17th
Remove asphalt curbing
Completed
June 21st-22nd
Mill off top surface of pavement(expect delays)
Completed
July 5th-9th
Raise castings to grade(expect delays)
Completed
July 27th
Install new drainage
Completed
July 28th-Aug. 20th
Install granite curbing and handi-cap ramps
Completed
Sept. 7th
Install new finish asphalt(expect delays)
Completed
Sept.14th
Install new asphalt curbing(expect delays)
On schedule
Sept 14th - Sept. 24th
Loam and seed
On schedule
Sept. 21st-24th
Repair driveway aprons, as necessary
On schedule

During construction there will be DELAYS and DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.

WILLIS LANE (NORTH HILL DRIVE TO POWDER HILL ROAD)


July 12th-July 23rd
Install drainage(expect delays)
Completed
July 28th
Lower castings
Completed
August 2nd
Reclaim roadway and grade
Completed
August 6th
Install binder course asphalt
Completed
Sept. 8th
Install granite throat stones and handi-cap ramps
On Schedule
Sept. 15th
Raise castings for finish pavement
On schedule
Sept. 27th
Install new finish pavement(expect delays)
On schedule
Sept. 30th
Install new asphalt curbing
On schedule
October 4th-8th
Repair driveway aprons(if necessary)
On schedule
October 4th-8th
Loam and seed
On schedule

DYNAMIC WARNING SIGN AT GIANNA DRIVE ( @ WALNUT STREET)


August 27th
Open sealed bids for sign
Completed
September 13th-17th
Install granite curb island
On schedule
Sept. 15th-Dec.31st
Installation of traffic loops, and dynamic warning sign
On schedule