2010 ROAD CONSTRUCTION PROGRAM
& SCHEDULE OF WORK
(last updated: September 8, 2010)
The Public Works Department has listed the following streets to be resurfaced during the 2010 construction season:
SALEM STREET ( Summer Street to Maple Street)
June 21st-22nd |
Mill off top surface of pavement(expect delays) |
Completed |
July 28th-29th |
Raise casting to grade (expect delays) |
Completed |
June 28th- Aug. 18th |
Install new granite curbing (expect delays) |
Completed |
August 31st |
Install finish pavement (expect delays) |
Completed |
Sept 14th |
Stripe roadway |
On schedule |
Sept.1st-14th |
Loam and seed |
On schedule |
July 26th-Sept 7th |
Repair sidewalk and driveway aprons as necessary |
Completed |
During construction there will be DELAYS and DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
THOMAS ROAD(Entire Length)
June 14th-17th |
Remove asphalt curbing |
Completed |
June 21st-22nd |
Mill off top surface of pavement(expect delays) |
Completed |
July 5th-9th |
Raise castings to grade(expect delays) |
Completed |
July 27th |
Install new drainage |
Completed |
July 28th-Aug. 20th |
Install granite curbing and handi-cap ramps |
Completed |
Sept. 7th |
Install new finish asphalt(expect delays) |
Completed |
Sept.14th |
Install new asphalt curbing(expect delays) |
On schedule |
Sept 14th - Sept. 24th |
Loam and seed |
On schedule |
Sept. 21st-24th |
Repair driveway aprons, as necessary |
On schedule |
During construction there will be DELAYS and DETOURS when paving work is scheduled. You may want to seek an alternate route. CAUTION should be exercised when traveling through the construction zone.Motorists and cyclists will drive on a grooved surface and need to manuever around raised manholes and traffic barrels.
Speed limits have been reduced to 25 MPH.
WILLIS LANE (NORTH HILL DRIVE TO POWDER HILL ROAD)
July 12th-July 23rd |
Install drainage(expect delays) |
Completed |
July 28th |
Lower castings |
Completed |
August 2nd |
Reclaim roadway and grade |
Completed |
August 6th |
Install binder course asphalt |
Completed |
Sept. 8th |
Install granite throat stones and handi-cap ramps |
On Schedule |
Sept. 15th |
Raise castings for finish pavement |
On schedule |
Sept. 27th |
Install new finish pavement(expect delays) |
On schedule |
Sept. 30th |
Install new asphalt curbing |
On schedule |
October 4th-8th |
Repair driveway aprons(if necessary) |
On schedule |
October 4th-8th |
Loam and seed |
On schedule |
DYNAMIC WARNING SIGN AT GIANNA DRIVE ( @ WALNUT STREET)
August 27th |
Open sealed bids for sign |
Completed |
September 13th-17th |
Install granite curb island |
On schedule |
Sept. 15th-Dec.31st |
Installation of traffic loops, and dynamic warning sign |
On schedule |
|